From November 19 to 21, 2024, the in-person meeting of Working Group 15-2 for the IEC 61400-15 wind resource assessment standard was held in Denver, USA. Hosted by ArcVera, the meeting adopted a hybrid online-offline format. More than 20 representatives from over ten institutions worldwide participated, including two experts from China General Certification Center (CGC) and Goldwind as Chinese delegates.

General Standard Updates
IEC 61400-15 (Assessment of wind resource, Energy yield and site suitability input conditions for wind power plants) is the first international standard providing guidance and specifications for wind resource assessment. It aims to refine assessment methodologies for wind resources, site suitability input conditions and energy yield of wind farms, and improve assessment accuracy. Meanwhile, it standardises and unifies the values and calculation procedures for energy yield assessment uncertainty, so as to eliminate substantial discrepancies in assessment results for identical projects among different consulting agencies.
Driven by strong end-user demand for site suitability provisions and the advanced drafting progress of this section, the Working Group decided at its 18th meeting in 2019 to split the standard into two sub-standards: IEC 61400-15-1 Site suitability input conditions for wind power plants and IEC 61400-15-2 Framework for assessment and reporting of the wind resource and energy yield.
As of July 12, 2024, IEC 61400-15-1 has been issued as FDIS (Final Draft International Standard) for member country voting, with official publication expected in 2025. Due to an extended drafting cycle, IEC 61400-15-2 was requested by the IEC Secretariat to discontinue the original project. A new NP (New Work Item Proposal) was resubmitted in June 2024 to restart standard development upon approval. This meeting marks the first in-person session after the project restart.
Meeting Progress
During the plenary discussion, the Working Group established its work plan and task list, targeting completion of the CD version of IEC 61400-15-2 by November 2025. Technical presentations and exchanges covered multiple topics, including the logic for uncertainty combination in multi-turbine energy yield calculation and the selection of correlation coefficients between masts, as well as validation of vertical extrapolation using only the two upper levels closest to hub height instead of the full measurement profile. Impacts brought by technical advances such as LiDAR scanning and large-scale atmospheric models on wind resource assessment were also discussed.
In breakout sessions, the two Chinese experts from CGC and Goldwind mainly contributed to the update of Clause 13 of the standard, “Energy yield assessment using operational data from existing wind farms near the proposed wind farm”. This method is not covered in conventional wind resource assessment. With the rapid growth of the wind power industry, many projects, especially in China, suffer from insufficient measurement data while operational wind farms exist nearby. Proper use of operational data from neighbouring operating wind farms can effectively compensate for inadequate measurement data at the proposed site, reduce uncertainty and improve the accuracy of energy yield assessment. This method aligns closely with industry trends and addresses key pain points in wind resource assessment, deserving special attention.
IEC 61400-15-1 has been finalised and is upcoming for release. Subsequent work will focus on supporting Chinese wind power practitioners to understand and apply this standard. IEC 61400-15-2 remains under development. China features a vast territory and wind farms with the most diverse terrain types globally, which means wind resource assessment engineers in China face some of the most challenging assessment conditions worldwide. CGC and Goldwind have participated in the drafting of this standard since 2016 and strived to incorporate characteristics of Chinese wind farms, though their impact has been limited by practical constraints. We call for more practitioners to engage in standard development and propose clauses better suited to China’s local conditions.